Energy & Grid | Enterprise | 8 MIN READ

Your next large site may not get power on your timetable

Capacity for large new grid connections is running short in parts of the grid, and the rules on who pays for upgrades are being rewritten.

By Marc Mendis •

In Brief

Any company planning a site that needs a large new grid connection should treat the connection date as the least certain number in its business case. On 21 October 2026, NEXTDC cut its revenue guidance after the local network suspended works to bring more power to its Melbourne campus. Regulators in Australia and overseas are moving to make large users pay to join the queue, pay for the upgrades they trigger and meet tougher technical standards. Boards should require the network business's written answer before approving the capital.

What happened at West Footscray

On 21 October 2026, data-centre operator NEXTDC told the ASX that the local network business, Jemena, had suspended works to increase the power supply to its M3 campus in West Footscray, Melbourne. Jemena paused the 66 kV network works in September after community opposition and problems gaining council access. NEXTDC does not expect the works to restart before February 2027, and has moved the site’s next increase in power to the 2027-28 financial year.

The delay hit revenue straight away. NEXTDC cut its revenue guidance for 2026-27 from $615-640 million to $475-500 million, mainly by taking out revenue from customers already signed up at the site. Those customers now wait longer for the capacity they contracted.

The same exposure applies to any project that needs a large new grid connection, such as an electrified factory, a hospital campus, an electric bus depot or a hydrogen plant. The network business assesses how much capacity it can offer and what upgrade the site needs, and the connection agreement sets who pays and when the site can be switched on. As NEXTDC found, councils and neighbours can also move the date. Revenue starts on that date, so a delay set by the network, the council or neighbours pushes back the company’s revenue.

Why connection dates are moving

Networks are being asked for far more capacity than they can build. By early 2026, proposed data centres were seeking about 30 times the grid capacity that operating data centres held, according to the Australian Energy Market Operator (AEMO). Many will never be built. More than a third of the projects AEMO tracked in 2025 have since been cancelled, including some that had been classed as committed.

Data-centre connection capacity in the NEM: operating and proposedThe queue is thirty times what is runningData-centre grid connection capacity in the National Electricity Market (GW)Operating, early 20262.2 GWProposed, 2025 assessment38 GWProposed, 2026 assessment67 GWProposed capacity covers 225 projects at all stages of the connection process, as advised by network businesses, February to May 2026.Source: AEMO, 2026 Electricity Statement of Opportunities, August 2026.

Sydney shows what a full network looks like. Transgrid, which runs the New South Wales transmission network, said in August that data centres in Western Sydney hold signed agreements for about 1.5 gigawatts (GW). It said its existing lines cannot take the further 20 GW of large loads that have asked to connect.

The rules are also moving cost and risk onto the companies that ask for capacity. The Australian Energy Market Commission (AEMC) writes the national electricity rules. It is consulting on proposals from energy ministers to make large users pay for the network upgrades they trigger, with a draft decision due by 1 April 2027. The NSW Parliament passed the state’s enabling bill on 14 October 2026, and the government has proposed that data-centre applicants pay an entry bond for each megawatt they request. Ireland already makes new data centres bring their own generation or storage, and Britain has proposed refundable fees to hold a place in the queue. National Cabinet plans national standards for AI infrastructure in 2027.

Companies are adapting. Some developers now pick sites for their grid capacity first. IREN chose its South Australian campus for its existing transmission access. Batteries, managed charging and flexible connection agreements can also lower the firm capacity a site has to request.

Three steps before the next capital approval

These steps are our recommendation for any project that needs a large connection, including sites the company plans to lease.

By 11 December 2026: list the exposed projects. Ask the CFO to list every project in the capital plan that needs a new or larger grid connection. For each one, record the capacity requested, what the network has said in writing and how much the company will have spent before the site can draw power. Give each project one executive owner for its connection.

By 26 February 2027: make the network’s answer a condition of approval. The investment committee should require the network’s written response in every paper for such a project, with the upgrade cost and a range of connection dates. Each paper should also price a 12-month and a 24-month delay, the position NEXTDC’s customers are now in. Ask whether a smaller firm connection backed by batteries or a flexible agreement could connect sooner. The board then sets the longest delay it will accept before management returns for a fresh approval.

By 31 March 2027: track reserved capacity like a lease. Ask general counsel to list each connection agreement’s milestones, the conditions for withdrawing capacity and any payment at risk. The chief operating officer reports slippage to the board risk committee each quarter. Engineers check equipment orders against the AEMC’s final technical standards before delivery.

Our recommended timetable for projects that need a large grid connection

Action Owner Timeline Priority
List every project needing a new or larger connection, with the capacity requested, the network's written position and spend before power; name one owner per project Chief financial officer By 11 December 2026 critical
Require the network's written response, a priced 12- and 24-month delay case and a flexible-connection option in every capital paper; set the board's delay limit Investment committee By 26 February 2027 high
Register connection milestones, withdrawal conditions and payments at risk; report slippage quarterly; check equipment against the AEMC's final standards General counsel and chief operating officer By 31 March 2027 high

Who else carries the cost of a late connection

NEXTDC’s customers show that a late connection reaches people outside the company. Lenders and customers plan around the date a site starts earning, and customers who wait too long may look for a connected site elsewhere. Both may ask the board what it knew about the connection date when it approved the project.

Other electricity users have a stake as well. The AEMC says its reforms aim to place the costs and risks of large connections on the businesses that create them. The aim is to keep households and other businesses from paying for upgrades, or for stranded assets when expected demand fails to arrive.

For the company itself, a delay brings carrying cost: land, design fees and equipment that earn nothing until the site is switched on. Any bond or upfront upgrade payment it could lose by walking away sits on top.

At its February 2027 meeting, the board should decide, project by project, how much capital it will release before the network’s written answer arrives. The CFO should bring the December list to that meeting, with each project’s written network position and delay cost.

Before February 2027, ask management: which project in our plan would we stop if its grid connection slipped by two years?

For your CFO and general counsel: the rules and the sources

Technical standards for large loads. AEMC, Improving the NEM access standards, Package 2 (ERC0394). The draft rule of 12 March 2026 would raise the threshold for large inverter-based loads connecting to distribution networks from 5 MW to 30 MW and add disturbance ride-through standards. The final determination is scheduled for 29 October 2026.

Who pays for network upgrades. AEMC, Cost recovery for network augmentations, Packages 1 and 2 (ERC0448 and ERC0456). Consultation paper 24 September 2026; submissions due 5 November 2026; draft determination due by 1 April 2027.

New South Wales. Electricity Infrastructure Investment Amendment Act 2026, passed 14 October and assented 23 October 2026. NSW DCCEEW consultation paper, August 2026: entry bond of $30,000 per MW of requested capacity, to be set by regulation.

National direction. National Cabinet, 26 August 2026; PM&C consultation paper on AI infrastructure (closed 9 October 2026), with tiers below 30 MW, 30 to 100 MW and above 100 MW.

Queue data. AEMO, 2026 Electricity Statement of Opportunities (August 2026, network data from February to May 2026). Transgrid, Sydney capacity announcement, 26 August 2026. NEXTDC, ASX release, 21 October 2026.

Overseas. Ofgem, demand-connection commitment fees, proposal of 29 July 2026. CRU (Ireland), data-centre connection policy, 12 December 2025. ACM (Netherlands), time-bound transport rights, 2026.

Questions for Leadership

Which projects in our capital plan need a new or larger grid connection, and which hold a written response from the network?

The board approves the capital, so it should see which approvals rest on an unconfirmed connection date.

How much will we have spent on each project before the site can draw power?

That sum is the capital at risk if the connection slips, and it grows with every month of delay.

What is the longest connection delay we will accept before management returns for approval?

A limit agreed in advance spares the board a rushed decision when a network date moves.

What happens to our reserved capacity if we miss a milestone in the connection agreement?

AEMO found cancellations among projects already classed as committed, so the board should know the terms that apply to ours.

Have our equipment orders been checked against the AEMC's final technical standards for large loads?

Equipment that cannot stay connected through grid disturbances may need changes before the network accepts it.

The Bottom Line

Make the network's written answer a condition of capital approval for any project that needs a large grid connection. Require the upgrade cost, a range of connection dates and a priced delay case in every paper, and set the board's delay limit by February 2027.

Frequently Asked Questions

What are regulators overseas doing about large new loads?

Britain's energy regulator proposed in July 2026 that new demand connections pay commitment fees of £237,500 to £712,500 per megawatt, refunded on connection and forfeited if the project drops out. Ireland requires new data centres to bring matching generation or storage and to buy new renewable electricity covering at least 80 per cent of their annual demand. The Dutch regulator has created an optional transport right on the high-voltage grid that provides capacity for at least 85 per cent of the time. In the United States, the federal energy regulator has opened proceedings on large-load cost recovery, security and flexible service.

Do these rules apply to companies that are not building data centres?

Some of them do. The AEMC's proposed technical standards cover large inverter-based loads, meaning sites that draw power through power electronics, such as data centres and hydrogen electrolysers. The cost recovery rule changes requested by energy ministers cover data centres and other large loads, and the NSW bond proposal applies to data-centre applicants. A factory or depot planned for a constrained area competes with nearby data centres for the same local capacity.

How much capacity should we ask the network for?

Ask for the demand the site will draw at each stage, with evidence. AEMO estimates that operating data centres used about 27 per cent of their connection capacity in early 2026, and that a mature fleet would average 45 to 51 per cent. Operators tell AEMO that new facilities take five to ten years to reach capacity. Under the NSW proposals, bonds would be charged per megawatt requested and connection agreements would include demand profiles, so an inflated request would cost more.

Will our own renewable supply or batteries speed up the connection?

They can reduce the firm capacity a site needs, which can widen its options. SA Power Networks offers flexible connections that combine a firm amount of capacity with extra capacity that can fall to zero when the network is stretched. The network business decides the physical connection, so ask it in writing what a battery or flexible agreement would change to the capacity it can offer.

Can we apply for connections at several sites and keep the best one?

New South Wales has proposed rules that would make that expensive. Its consultation paper proposes that data-centre applicants disclose whether they or a related entity are pursuing a substantially similar application elsewhere in Australia. The proposed entry bond could be forfeited if an applicant fails to provide required information on time or stops engaging with the network. The paper reports that a utility in Ohio introduced deposits, minimum bills and termination fees for large loads, after which its connection requests fell from 30 GW to 13 GW.